Dynamics 365 go live training plan: what finance and operations teams need before and after go live

A Dynamics 365 training plan for go live trains four groups at three moments. Key users learn the solution 8 to 10 weeks before go live, because they test it and later teach it. End users train in short, role based sessions 2 to 4 weeks before go live, on migrated data in a test environment. Managers and approvers learn the decisions the system now asks of them, and support staff learn to answer first line questions. After go live, the plan continues for 4 to 8 weeks with floor support, first period close coaching and refreshers.

Most training plans fail on timing rather than content. Sessions held too early are forgotten by cutover weekend, sessions held on demo data teach screens rather than work, and plans that stop on go live day leave finance alone at its first month end. This guide sets out a plan that avoids all three.

Key facts at a glance:

• Four audiences. Key users, end users by role, managers and approvers, and first line support each need a different plan.
• Timing. Key users train 8 to 10 weeks before go live, end users 2 to 4 weeks before, close enough to remember.
• Real data. End user training works best on migrated data in a test environment, after acceptance testing is signed off.
• After go live. Plan 4 to 8 weeks of floor support, office hours and coaching through the first period close.
• Why it pays. Prosci research links excellent change management to 88 percent of projects meeting objectives, against 13 percent for poor programmes.
• Best first step. Map every role to the processes it runs in Dynamics 365 before writing a single training session.

‍

What should a Dynamics 365 training plan include?

A useful training plan starts from roles, not from modules. An accounts payable clerk, a warehouse operator and a controller all touch Dynamics 365 Finance and Operations, but each runs a handful of processes and needs to run them well on day one. The plan therefore begins with a role map: every job title, the processes it performs, the security role it will hold and the number of people in it. From that map follow the sessions, the materials and the order in which people are trained. Microsoft's own guidance on building a training strategy for Dynamics 365 implementations makes the same point: training objectives should be defined per audience and tied to the business processes in scope.

The plan also needs owners. Key users are the backbone, because they test the solution, adapt materials to local practice and become the first port of call for colleagues. If they are treated as a part time role, a pattern we describe among the most common Dynamics 365 implementation mistakes, both testing and training suffer at the same time. Finally, the plan needs measures: who attended, who passed a short practical check, and which processes generate the most questions after go live. Without them, a steering committee sees a green status for training while half the warehouse has never logged in to the test environment.

Audience What they learn When Format
Key users Full processes in their area, configuration logic, exceptions, how to support colleagues 8 to 10 weeks before go live, during testing Workshops with the implementation team, hands on in test
End users The five to ten tasks of their role, end to end, on their own data 2 to 4 weeks before go live Short role based sessions led by key users
Managers and approvers Approvals, workflows, dashboards and the decisions the system now requires 2 to 3 weeks before go live Briefings and short demonstrations
Finance close team Period close, reconciliations, reporting and intercompany steps Before go live and again before the first month end Rehearsal of a full close in test
First line support Common questions, known issues, how to log and escalate tickets 1 to 2 weeks before go live Session with the support partner
New joiners after go live Role tasks with current processes and materials Ongoing Recorded sessions, guides and buddy support

‍

How do you prepare key users to train their colleagues?

A train the trainer model is the only way most midsize companies can reach hundreds of users in a few weeks, but it works only if key users are prepared for the role rather than simply invited to it. Preparation has three parts. First, key users need deep process knowledge, which they gain by designing and testing the solution with the implementation team rather than by attending a separate course. Second, they need materials they can adapt: a session outline per role, practice scenarios built on real documents, quick reference cards and a short practical check at the end of each session. Third, they need time, which means a written agreement with their managers about how many hours per week the role takes during the training window.

It also helps to pair key users across functions. A finance key user who sits in on a warehouse session understands why receipts post the way they do, and a warehouse key user who sees the period close understands why a late goods receipt matters to finance. These pairings surface integration questions before go live and create a small network of people who can answer cross functional questions in the first weeks. Companies that skip this preparation usually discover the gap during the first end user sessions, when key users cannot answer why a process works the way it does and confidence in the new system drops before it has gone live.

A simple readiness check before end user training starts protects the plan. Each key user runs one session for the project team, using the real materials and a test environment loaded with migrated data, and the team agrees what to fix. It takes a day per area and saves weeks of uneven sessions later.

‍

__wf_reserved_inherit

When should Dynamics 365 end user training happen?

End user training has a narrow window. Held more than a month before go live, it fades before people need it, and in large projects the solution often changes after training because testing finds issues. Held in the last few days, it competes with cutover and leaves no time for practice. The practical window is two to four weeks before go live, after user acceptance testing is signed off, so the screens and processes people learn are the ones they will use. Sessions should be short, no more than half a day per role, and followed by practice time in the test environment with tasks people recognise from their own work.

The data matters as much as the timing. Training on a demo company teaches navigation, but a buyer who sees real vendors, real items and real price agreements learns the job. That requires a test environment loaded from a recent data migration rehearsal, which most projects have anyway at this stage. The sequence also matters: train approvers before the people who submit to them, and train the finance close team before the first month end rather than only before go live. Where shifts or several countries are involved, plan sessions per site and language, and record them so that people who miss a slot can catch up without delaying the plan.

‍

How should finance and operations teams be trained differently?

Finance and operations teams use Dynamics 365 in different rhythms, and the training plan should follow those rhythms. Finance work is periodic and judgement heavy: invoices are matched and approved daily, but the critical moments are the month end close, reconciliations, accruals and reporting. Finance training should therefore include a rehearsal of a full period close in the test environment, with the actual sequence of tasks, owners and checks. Controllers also need to understand where the numbers come from, which means short sessions on how operational postings flow into the general ledger and how financial dimensions are set.

Operations work is continuous and repetitive: receiving, picking, production reporting and shipping happen every hour, often on mobile devices and often by people who rarely sit at a desk. Here training should happen where the work happens, on the warehouse mobile app or at the production terminal, in short sessions that fit around shifts. Quick reference cards and in app guidance matter more than long manuals. Finally, both groups need to know what changed rather than only how to use the system. People accept new steps faster when they understand why an approval or a scan now exists, which is where change management and training meet.

‍

What happens to training after go live?

Go live is the moment when training becomes real. Questions that never appeared in a classroom arrive in the first days, and the speed at which they are answered decides whether people trust the new system or start building workarounds in spreadsheets. A good plan provides floor support in the first one to two weeks, with key users and consultants visible in the main locations, daily office hours for questions, and a simple way to log issues. The finance team should be coached through its first month end in the new system, ideally by the same people who led the close rehearsal.

The plan then moves from support to reinforcement. Short refresher sessions after four to six weeks target the processes that generated the most tickets, and materials are updated with the answers. Adoption should be measured, not assumed: completion of key tasks in the system, the number of support tickets per user and the share of work still done outside Dynamics 365. The effort pays back. Prosci reports that 88 percent of projects with excellent change management met or exceeded their objectives, against 13 percent of those with poor change management. Training is the most visible part of that change effort, and it does not end on cutover weekend. Microsoft's continuous updates to Dynamics 365 also change screens and features several times a year, so a light update briefing for key users belongs in the plan long after the project team has gone.

Measure What it shows Target direction
Key tasks completed in the system Whether people do their work in Dynamics 365 Rising each week after go live
Support tickets per user Where understanding is weak Falling after the second week
Repeat questions on the same process Gaps in materials or sessions Falling after refreshers
Work done outside the system Workarounds in spreadsheets or email Close to zero by the first close
Time to complete period close Finance confidence with new processes Back to target within two closes

‍

Why training is a business risk, not a line item

Training is usually the first budget line to be trimmed when an ERP project runs over, and it is one of the most expensive to cut. When users are not ready on go live day, the cost does not disappear; it moves into the operation. Invoices wait because approvers do not know where to find them, orders are entered twice because nobody trusts the first one, and the finance team works evenings through its first close because journals and reconciliations look different. Those costs are real, but they are spread across departments and rarely traced back to the training decision that caused them.

For a sponsor, the useful question is not how many hours of training were delivered but how much operational disruption the business can tolerate in the first two months, and what level of readiness is needed to stay within it. Framed that way, training becomes a risk control with an owner and a target, like data reconciliation or cutover rehearsal. It also changes who is accountable. The partner can design and deliver the sessions, but only line managers can release people to attend, and only the business can decide that a team is not ready. Making that explicit in the project charter is one of the cheapest ways to protect the go live date and the first close.

A simple way to keep this visible is to give training the same status in steering reports as data and testing. A single line showing the share of critical roles trained, the results of practical assessments and the open readiness actions lets sponsors see early when a department is falling behind, while there is still time to add sessions or move key users onto the problem rather than discovering it after cutover.

‍

__wf_reserved_inherit

How should leadership decide whether users are ready for go live?

A go live decision should include a readiness check for people, just as it includes one for data and integrations. The check works best when it is based on evidence rather than attendance lists. Each key user confirms that the processes in their area can be run end to end on migrated data. Each team completes a short practical assessment, such as posting a vendor invoice with a variance or releasing a production order, rather than a quiz. Managers confirm that approvers know what the system will ask of them, and the support desk confirms that first line answers for the most common questions are ready.

Leadership should agree the thresholds in advance, for example that every critical role has at least two trained people and that no team is below an agreed share of successful practical assessments. If a team falls short, the options are clear: extra sessions, more floor support in the first weeks, or in rare cases a later start for that area. What leadership should avoid is a go live where readiness was never measured, because then the first sign of a problem is a missed payment run or a late month end, and by that point the cost of fixing it is far higher than the cost of one more week of preparation.

‍

How ANEGIS supports go live training

ANEGIS runs role based Dynamics 365 user training for end users, key users and administrators, built on each client's real processes rather than general theory. Training combines practical workshops, materials and in app guidance, and is planned together with the implementation, so sessions use migrated data and follow acceptance testing rather than competing with it. Where the change is larger, ANEGIS combines training with change management for the ERP implementation, so that people understand why processes change as well as how.

The same delivery team of more than 125 people that implements Dynamics 365 Finance and Operations supports clients through go live and hypercare, which is why training does not stop at cutover. Floor support, first close coaching and refresher sessions are planned from the start, and knowledge moves to the client's key users so that new joiners can be trained internally. Nine in ten ANEGIS clients stay with the company after go live, which reflects how much of the value of an implementation is decided in the weeks after launch rather than before it.

Planning training for your Dynamics 365 go live

A training plan works best when it is built together with the cutover plan, not after it. Contact ANEGIS to book a free consultation on training and adoption for your Dynamics 365 project.

‍

FAQs

When should Dynamics 365 end user training start?

Two to four weeks before go live, after acceptance testing is signed off. Earlier sessions are forgotten and may cover screens that change; later sessions compete with cutover. Key users should start much earlier, 8 to 10 weeks before go live.

Should we train on demo data or our own data?

Your own data. A test environment loaded from a recent migration rehearsal lets people practise their real tasks with real vendors, customers and items, which makes training stick and exposes data issues before go live.

How long should end user training sessions be?

Short. Half a day per role is usually enough for the five to ten tasks a role performs, followed by practice time. Long sessions covering whole modules overload people and are forgotten quickly.

What should happen in the first month after go live?

Floor support in the first one to two weeks, daily office hours, coaching through the first month end and refreshers after four to six weeks, targeted at the processes that generated the most support tickets.

Does ANEGIS provide Dynamics 365 end user training?

Yes. ANEGIS runs role based training for end users, key users and administrators on each client's real processes, with workshops, materials and in app guidance, and supports teams through go live and the first period close.

See more

Partner Dynamics 365

7 ways Microsoft partners can add Dynamics 365 Finance and Operations delivery capacity without hiring

Read article
Text Link
Dynamics 365 F&O

Who can give a second opinion on our Dynamics 365 project, and what does the review cover?

Read article
Text Link
Dynamics 365 F&O

Why do Dynamics 365 implementations fail, and how do you recover a project in trouble?

Read article
Text Link
Back to all

Looking for a Microsoft partner? Let's talk about your project

Work with a team that has delivered implementations and projects for dozens of companies. Schedule an introductory call and see:

How to tailor Dynamics 365 to your company's processes, rather than the other way around

Which areas are worth automating to save time and reduce costs

Here is the step-by-step implementation process with Anegis: from analysis to post-launch support