Who can give a second opinion on our Dynamics 365 project, and what does the review cover?

A second opinion on a Dynamics 365 project can come from an independent Dynamics 365 partner that is not delivering the project, from Microsoft through FastTrack for eligible customers, from an advisory or audit firm, or from experienced independent architects. A useful Dynamics 365 implementation review covers scope against business objectives, solution architecture, code and extensions, data and migration, integrations, testing, project governance and the contract. It ends with a clear statement of what to keep, what to fix and what it will really cost to finish.
Boards ask for a second opinion at predictable moments: before releasing the next budget tranche, after a second postponed go live date, or when status reports stay green while the people doing the work say otherwise. The value of the review lies less in finding problems, which are usually known inside the project, than in turning them into facts that sponsors can act on without assigning blame.
Key facts at a glance:
• Who can review. An independent Dynamics 365 partner, Microsoft FastTrack for eligible customers, an advisory firm or independent architects.
• What it covers. Scope, architecture, code and extensions, data, integrations, testing, governance and the contract.
• Typical duration. Around two weeks for a focused review of a midsize Finance and Operations project.
• Best timing. Before a funding decision or a go live decision, not after the next date has slipped.
• Independence. Ask every reviewer to declare whether it would bid for follow on work, and judge the report with that in mind.
• Main output. A risk map, a recommendation to stabilise, replan or change scope, and a realistic estimate to completion.
When does a Dynamics 365 project need a second opinion?
Most projects that end up in trouble showed the signals months earlier. The go live date moves for the second time with a new justification but no new plan. Each round of user acceptance testing produces as many defects as it closes. Migrated balances still do not reconcile after the third data load. Integrations work in demonstrations but have never run on real volumes. Your own finance controller is writing specifications that the partner should have written. Consultants on the partner side change, and the architect who understood the original design is no longer involved. Any one of these can be explained away; two or three together usually mean the project has lost the ability to correct itself.
The best time for a Dynamics 365 project second opinion is before a decision rather than after a failure. Natural points are the end of analysis and design, before the build is too far along; before the next payment or budget tranche; and before the go live decision, when the pressure to launch is highest. A review at those points is cheap compared with the cost it can prevent. Many of the patterns it looks for are described in our article on twelve Dynamics 365 Finance and Operations implementation mistakes.

Who can give an independent second opinion?
Four kinds of reviewer are realistic, and each brings a different mix of depth and independence. An independent Dynamics 365 partner that is not delivering the project brings hands on knowledge of Finance and Operations code, data and integrations, and can judge quickly whether a design will survive updates and real volumes. Microsoft FastTrack offers architectural guidance and reviews for customers that meet its eligibility criteria, aligned with Microsoft's own methodology, though it does not take responsibility for delivery. Advisory and audit firms are strong on governance, contracts and programme management but may need specialist support for code and data. Independent architects can be excellent, provided their individual experience matches your industry and modules.
Independence deserves an honest look. A partner that reviews a project may later be asked to complete it, which some boards see as a conflict of interest and others as a benefit, because the reviewer already understands the project if a takeover becomes necessary. The practical answer is transparency: ask each reviewer to state upfront whether it would bid for follow on work, ask for the evidence behind every finding, and make sure the report belongs to you and can be used with any partner. A reviewer that recommends keeping your current partner when that is the right answer has earned trust.
| Reviewer | Strength | Limitation |
|---|---|---|
| Independent Dynamics 365 partner | Deep Finance and Operations knowledge of code, data and integrations | May bid for follow on work, so ask it to declare this |
| Microsoft FastTrack | Aligned with Success by Design, access to Microsoft expertise | Available to eligible customers; advisory, not delivery |
| Advisory or audit firm | Governance, contracts, programme management | May lack hands on Finance and Operations depth |
| Independent architect | Senior individual expertise, flexibility | Single person capacity and limited coverage of all areas |
| Internal audit | Knows the organisation and its controls | Rarely has ERP delivery experience |
What a Dynamics 365 implementation review covers
A Dynamics 365 implementation review should examine the whole project, not only the part that is visibly failing, because the visible problem is usually a symptom. Eight areas cover almost every case. Scope and business processes are compared with the original objectives to see what has been deferred. Solution design and architecture are checked for decisions that cascade, such as the chart of accounts, financial dimensions and intercompany setup. Code and extensions are reviewed for whether they modify standard objects or are built as extensions that survive updates. Data and migration, integrations and testing are tested against evidence rather than reports. Governance and decision making, and finally the contract, team and environments, complete the picture.
The difference between a useful review and a polite one is evidence. Each finding should point to something the reviewer saw: a reconciliation report, a defect register, a code sample, a test result, a decision log. The table below shows the questions and evidence for each area, and it can double as a checklist when you brief a reviewer. Give the reviewer read access to environments and repositories from the first day; a review that relies on interviews and slides alone tends to confirm what the project already believes about itself.
| Area | Key question | Evidence to examine |
|---|---|---|
| Scope and processes | What has been deferred, and does the remaining scope meet the business case? | Original objectives, change log, process maps |
| Architecture | Are the chart of accounts, dimensions and intercompany design sound? | Solution blueprint, configuration, design documents |
| Code and extensions | Are customisations built as extensions that survive updates? | Code repository, extension list, update test results |
| Data and migration | Do migrated balances reconcile with the source system? | Trial load reports, reconciliations, data quality logs |
| Integrations | Have interfaces been tested on real volumes and exceptions? | Integration test results, monitoring, error logs |
| Testing | Is the defect trend falling and are sign offs unconditional? | Defect register, UAT results, test coverage |
| Governance | Who decides, and are decisions being made? | Steering committee minutes, RAID log |
| Contract, team, environments | Are obligations, staffing and environments fit to finish? | Contract, team plan, environment inventory |
Borrow the gateway model from major public projects
Independent review at decision points is standard practice in large public programmes, and private companies can borrow the idea. In the UK, the assurance review toolkit published by the National Infrastructure and Service Transformation Authority describes gateway reviews at each stage of a major project, from strategic assessment through to operations and benefits realisation, with the purpose of giving the senior responsible owner support and challenge before key decisions. The reviews are short, evidence based and timed to approvals, which is exactly what a Dynamics 365 project needs.
Microsoft's own Success by Design framework follows a similar logic for Dynamics 365. A Solution Blueprint Review assesses the high level design early, implementation reviews go deeper into areas such as data, security, integration and testing, and a Go Live Readiness Review checks cutover plans, user acceptance testing and support readiness before production. An independent second opinion is most valuable when it uses the same reference points, because findings can then be discussed with the partner in a shared language rather than as a dispute between opinions. Building two or three such gates into your own governance turns a second opinion from an emergency measure into routine assurance, and makes the next review far less awkward for everyone involved.

What a useful second opinion report looks like
The report is the product, so it is worth specifying before the review starts. Boards rarely need more than a few pages of findings, but they need them to be direct. A good report names the two or three root causes rather than listing fifty symptoms, separates what is genuinely broken from what is merely unfinished, and recommends one course of action among a small number of real options. It also states plainly what it will cost in time and money to reach go live, because that number is what the sponsor will be asked about first. Agree in advance who receives the report and when. A review presented first to the sponsor, then discussed with the partner and the project team, and only then taken to the board gives everyone a chance to correct facts without diluting conclusions.
A useful report usually contains the following elements:
• Findings without softening. Root causes stated clearly, each backed by evidence the reviewer examined.
• Keep, fix, discard. Every major element of the solution classified, so the value of work already done is visible.
• Risk map. The risks that could still stop go live, ranked by impact and likelihood.
• Recommended path. Stabilise and continue, replan, reduce scope or, in rare cases, reimplement.
• Estimate to completion. A realistic schedule and budget built backwards from go live readiness criteria.
• Board summary. Findings expressed as business decisions rather than technical detail.
How should sponsors act on the findings of a review?
A second opinion is only as useful as the decisions it leads to. The most common mistake after a review is to treat the report as a verdict on the past rather than as a plan for the future. Sponsors should take the findings into a dedicated steering meeting, with the delivery partner present, and leave with three outcomes: an agreed view of where the project really stands, a revised plan with a realistic go live date, and a short list of decisions that only the sponsors can make, such as reducing scope, adding budget or changing people in key roles.
Tone matters as much as content. A review that is used to assign blame encourages the delivery team to defend its position, while the same findings presented as a shared starting point make it easier to fix the problems that matter. Sponsors should also decide how progress against the revised plan will be checked. A short follow up review after six to eight weeks, measuring the same areas as the original one, is a practical way to confirm that the recovery is working and to adjust early if it is not. Without that follow up, recommendations tend to fade as soon as the next deadline arrives.
Should you stay with your current partner or change it?
A second opinion often raises the question of whether the current partner should stay. In most cases the answer is yes, at least for the next phase. Changing partners in the middle of a Dynamics 365 project carries its own risk: knowledge of the design and the extensions has to be transferred, a new team needs time to understand the system, and the company pays twice for part of the learning curve. A review that finds fixable problems in governance, testing or data usually supports a reset with the same partner, under clearer rules and with the findings written into the plan.
Changing partner becomes the better option when the review shows problems that the current partner cannot or will not fix: a solution design that does not fit the business and that the partner defends rather than revisits, a team without the Finance and Operations depth the project needs, or a breakdown in trust that makes honest reporting impossible. Even then, the change should be planned as a structured transition with a defined handover period, access to code and environments secured in advance, and a fixed scope for the first phase under the new partner. Sponsors who make this choice on evidence rather than frustration usually recover faster, whichever way they decide.

How can the next project avoid needing a rescue?
Most of the problems a second opinion finds could have been prevented by a handful of practices set at the start. Companies that have been through a difficult Dynamics 365 project often build these into their next programme, and they work equally well for a first implementation. The ones with the strongest effect are simple to describe:
• Independent checkpoints. Short reviews at the end of design, before user acceptance testing and before go live, agreed in the contract.
• One version of the truth. A steering report with budget, contingency, defects and reconciliation status on a single page.
• Named people. Key roles on the partner side named in the contract, with a process for agreed replacements.
• Business ownership. Process owners who sign off design and testing, rather than leaving acceptance to IT.
• Standard first. A written rule that every extension needs a business case approved by the steering committee.
None of these practices is expensive, and together they cost far less than a single postponed go live. Their value is that they make problems visible while they are still small, so that sponsors decide on facts rather than discovering the real state of the project only when a deadline is missed.
How ANEGIS runs a second opinion on Dynamics 365 projects
ANEGIS offers an independent second opinion as part of its Dynamics 365 project recovery service. It starts with a two week project audit at a fixed price, delivered with the project team through a review of environments and documentation and workshops with business representatives. The audit examines the eight areas described above and is conducted within the Success by Design framework, so the project is measured against the model Microsoft recognises. It ends with a findings report presented without softening, a risk map, a recommended course of action, a plan to complete the project and an estimate of the cost to completion, all of which belong to the client regardless of what it decides next.
The audit carries no commitment to further work. If the conclusion is that the project is best completed with the current partner, ANEGIS says so. Where the board wants continuing assurance, ANEGIS can take a standing quality assurance role at key checkpoints and report directly to the sponsor, including a go live readiness review before the final decision. If a takeover proves necessary, the team already understands the project and does not start from the beginning. ANEGIS has worked with the platform for over twenty years, from Axapta 3.0 to Dynamics 365, and serves international groups from offices in Poland and the UK.
Need an independent view of your Dynamics 365 project?
A two week review is usually cheaper than another month of delay. Contact ANEGIS to book a free consultation about a second opinion on your project.
FAQs
Who can give a second opinion on a Dynamics 365 project?
An independent Dynamics 365 partner that is not delivering the project, Microsoft FastTrack for eligible customers, an advisory or audit firm, or experienced independent architects. Choose a reviewer with hands on Finance and Operations depth and clear independence.
How long does a Dynamics 365 project review take?
A focused review of a midsize Finance and Operations project usually takes about two weeks, combining documentation and environment reviews, workshops with key users and technical analysis of code, data, integrations and test results.
Do we need to tell our current partner?
Usually yes, because the reviewer needs access to environments, code and documentation. Present it as standard assurance before a funding or go live decision rather than as an accusation; good partners welcome evidence based reviews.
Will the reviewer try to take over our project?
Some reviewers may bid for follow on work. Ask every reviewer to declare this upfront and to back each finding with evidence. ANEGIS audits carry no commitment to further work, and the report belongs to you.
What does the review cost compared with a delay?
A fixed price review of about two weeks typically costs less than one additional month of a stalled project, when partner fees, internal team time and the cost of running the legacy system are added together.
See more

7 ways Microsoft partners can add Dynamics 365 Finance and Operations delivery capacity without hiring

Why do Dynamics 365 implementations fail, and how do you recover a project in trouble?

Dynamics 365 go live training plan: what finance and operations teams need before and after go live
Looking for a Microsoft partner? Let's talk about your project
Work with a team that has delivered implementations and projects for dozens of companies. Schedule an introductory call and see:
How to tailor Dynamics 365 to your company's processes, rather than the other way around
Which areas are worth automating to save time and reduce costs
Here is the step-by-step implementation process with Anegis: from analysis to post-launch support